eSconnect Project Presentation phase wise ..

Project Phase wise plan for Phase 1 - 2011-12

Starting with 5 BLock in 5 District -- Feb 2011 - Rs. 6,95,80,000

1 Block Budget - 13916000 -- 1.4 Crore

Next - Whole Per District -- 5 District - 11 Block per district -- = 55 = 77 Crore

Total in per State (Bihar) - 35 District for first 3 year , total block 1925 = Budget 2,695 Crore

Per BLock No of Jobs - 20 * 1925 = 38500 New Jobs

Total School Covered - 140 * 1925 = 2,69,500 ~ 3lac

Total Students Benefited -- 21000 * 1925 = 4,04,25,000 ~ 4 Crore +

Total Village Covered - 140 * 1925 = 2,69,500 ~ 3lac